Unprogrammed Appropriations 202323I00216

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SUHI RIVER (DOWNSTREAM) INCLUDING ROAD RIGHT OF WAY, PHASE 1-B, TACLOBAN CITY

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SUHI RIVER (DOWNSTREAM) INCLUDING ROAD RIGHT OF WAY, PHASE 1-B, TACLOBAN CITY is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱134,810,892.64. Status: Past target date (DPWH On-Going). Contractor on record: EZJONES CONST INC. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

287 projects · ₱36.2B total · 7 flags

Other projects by this contractor

View all 287 projects →

4. Implementation

Contract Amount

₱134,810,892.64

Progress

Past target date (DPWH On-Going)

Start Date

February 13, 2024

Target End

September 3, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.