Roads23AA0179

SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR LIGHTS ALONG MANILA NORTH ROAD BACARRA-PASUQUIN SECTION

SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR LIGHTS ALONG MANILA NORTH ROAD BACARRA-PASUQUIN SECTION is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱47,504,732.91. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: MG SAMIDAN CONST. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigating Structure and Highway drainage along National Road (Narapunan Creek), Barangay Davila, Pasuquin, Ilocos Norte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Ilocos Norte 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

533 projects · ₱51.8B total · 52 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, KAMOG JCT. - CALOT - PAPPA - BAGONG - BALLUAY - TUEL JCT

Cordillera Administrative Region, Cordillera Administrative Region

2022₱289.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS ITOGON - DALUPIRIP - SN MANUEL BDRY ROADKO275+510 -

Cordillera Administrative Region, Cordillera Administrative Region

2021₱279.9M
Reported complete (DPWH)
No sat.

BAGUIO - BONTOC RD - KO347+520 - KO347+577BAUKO, MT. PROVINCE

Cordillera Administrative Region, Cordillera Administrative Region

2022₱241.3M
Reported complete (DPWH)
No sat.

SPECIAL ROAD PROJECT - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF ROAD SAFETY DEVICES ALONG A. SN FERNANDO AIRPORT RD - K0265 + (-273)-K0265 + (-128) - K0266 + 828-K0267 + 015, BARANGAY PAGDALAGAN. BARANGAY SAN VICENTE, BARANGAY

Region I, Region I

2023₱241.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - PREVENTIVE MAINTENANCE (ASPHALT OVERLAY) ALONG GOV. BADO DANGWA NATIONAL RD (S00377LZ) KO328+(-085) - KO329+420, (S00376LZ) KO320+100 - KO3

Cordillera Administrative Region, Cordillera Administrative Region

2022₱212.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ROAD, CAMP 1 - TABAAN SUR - TABAAN NORTE - TALOY SUR ROAD TO MARCOS HIGHWAY, TUBA, BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2022₱212.3M
Reported complete (DPWH)
View all 533 projects →

4. Implementation

Contract Amount

₱47,504,732.91

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 29, 2023

Target End

September 20, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.