GAA 2025 SSP25CN0100

CONSTRUCTION OF DRAINAGE CANAL, BARANGAY CADAYACAN, MARIA AURORA, AURORA

CONSTRUCTION OF DRAINAGE CANAL, BARANGAY CADAYACAN, MARIA AURORA, AURORA is a DPWH-tracked public work in Aurora DEO, Region III. Reported contract value: ₱15,131,333.75. Status: Past target date (DPWH On-Going). Contractor on record: JOHN DEE B BUSTAMANTE CONST 30458. Figures trace to dpwh.

Aurora DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱15,131,333.75

Progress

Past target date (DPWH On-Going)

Start Date

July 4, 2025

Target End

December 18, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.