Flood Control and Drainage18HD0037

CONSTRUCTION OF FLOOD CONTROL OF OLIVO BRIDGE ALONG OLIVO RIVER, TABUELAN, CEBU

CONSTRUCTION OF FLOOD CONTROL OF OLIVO BRIDGE ALONG OLIVO RIVER, TABUELAN, CEBU is a DPWH-tracked public work in Cebu 4th DEO, Region VII. Reported contract value: ₱9,306,937.35. Status: Reported complete (DPWH). Contractor on record: CYJE FIRST BUILDERS CONST CORP FORMERLY: FIRST BUILDERS AND DEVELOPERS. Figures trace to dpwh.

Cebu 4th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure of Olivo Bridge along Olivo River, Tabuelan, Cebu
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-18-0032654

₱214,303.00 · FY2018

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱9,306,937.35

Progress

Reported complete (DPWH)

Start Date

June 6, 2018

Target End

October 12, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.