Flood Control and Drainage25DB0108

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJ FLOODS- FLOOD MANAGEMENT PROG- CONST/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SEAWALL PROTECTION STRUCTURE, BARANGAY CARRENAHAN, BALAYAN,BATANGAS

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJ FLOODS- FLOOD MANAGEMENT PROG- CONST/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SEAWALL PROTECTION STRUCTURE, BARANGAY CARRENAHAN, BALAYAN,BATANGAS is a DPWH-tracked public work in Batangas 1st DEO, Region IV-A. Reported contract value: ₱19,012,000.00. Status: Past target date (DPWH On-Going). Contractor on record: 11-16 CONST 29646. Figures trace to dpwh.

Batangas 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure in Barangay Malibu, Tuy, Batangas
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Batangas 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 29646

205 projects · ₱17.1B total · 0 flags

4. Implementation

Contract Amount

₱19,012,000.00

Progress

Past target date (DPWH On-Going)

Start Date

March 31, 2025

Target End

September 26, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.