CONSTRUCTION OF FOUR STOREY EIGHT CLASSROOM - LOLOMBOY NHS BOCAUE, BULACAN

CONSTRUCTION OF FOUR STOREY EIGHT CLASSROOM - LOLOMBOY NHS BOCAUE, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱12,725,082.71. Status: Reported complete (DPWH). Contractor on record: LE REVE BUILDERS. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱23,994,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Bocaue River at Binang 1st Section, Bocaue, Bulacan
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-16-0014765

₱4,044,848.00 · FY2016

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱12,725,082.71

Progress

Reported complete (DPWH)

Start Date

February 21, 2017

Target End

August 19, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.