Roads23CH0093

CONCRETING OF BRGY. VILLA MARIA FMR, BRGY. VILLA MARIA, PORAC, PAMPANGA

CONCRETING OF BRGY. VILLA MARIA FMR, BRGY. VILLA MARIA, PORAC, PAMPANGA is a DPWH-tracked public work in Pampanga 2nd DEO, Region III. Reported contract value: ₱11,929,174.38. Status: Reported complete (DPWH). Contractor on record: GEOHEART CONST. Figures trace to dpwh.

Pampanga 2nd DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱47,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Maintenance of Flood Mitigation Structures along Quitangil River, Magalang, Pampanga - Phase 1
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Pampanga 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱11,929,174.38

Progress

Reported complete (DPWH)

Start Date

July 10, 2023

Target End

February 4, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.