Flood Control and Drainage24C00510

BASIC INFRASTRUCTURE PROGRAM-BIP-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF FLOOD CONTROL STRUCTURES,ANYATAM-MAPANIQUE CREEK, SAN ILDEFONSO, BULACAN (PHASE 10)

BASIC INFRASTRUCTURE PROGRAM-BIP-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF FLOOD CONTROL STRUCTURES,ANYATAM-MAPANIQUE CREEK, SAN ILDEFONSO, BULACAN (PHASE 10) is a DPWH-tracked public work in Region III, Region III. Reported contract value: ₱97,514,202.10. Status: Past target date (DPWH On-Going). Contractor on record: L R TIQUI BUILDERS INC. Figures trace to dpwh.

Region III, Region III
Region: Region III

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

380 projects · ₱29.1B total · 8 flags

Other projects by this contractor

View all 380 projects →

4. Implementation

Contract Amount

₱97,514,202.10

Progress

Past target date (DPWH On-Going)

Start Date

May 14, 2024

Target End

April 8, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.