GAA 2024 OO-124K00010

CONST. OF BY-PASS AND DIVERSION ROADS, MAGSAYSAY-BUTUAN CITY COASTAL BY-PASS/ALTERNATE ROAD, PACKAGE 5. MISAMIS ORIENTAL

CONST. OF BY-PASS AND DIVERSION ROADS, MAGSAYSAY-BUTUAN CITY COASTAL BY-PASS/ALTERNATE ROAD, PACKAGE 5. MISAMIS ORIENTAL is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱89,829,410.75. Status: Reported complete (DPWH). Contractor on record: TRIPARCO DEVELOPMENT CORP. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

357 projects · ₱29.2B total · 4 flags

Other projects by this contractor

View all 357 projects →

4. Implementation

Contract Amount

₱89,829,410.75

Progress

Reported complete (DPWH)

Start Date

May 23, 2024

Target End

February 16, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.