Water Provision and Storage21LH0169

CONST. OF RAINWATER COLLECTION SYSTEM AT 1) TIBULOY BRGY. HALL, BRGY. TIBULOY, D.C. 2) TIBULOY ES, BRGY. TIBULOY, D.C. 3) ATAN-AWE BRGY. HALL, BRGY. ATAN-AWE, D.C. 4) SIBULAN BRGY. HALL, BRGY. SIBULAN, D.C. 5) MT. APO ES, BRGY. SIBULAN, D.C. 6) LAMANAN BG

CONST. OF RAINWATER COLLECTION SYSTEM AT 1) TIBULOY BRGY. HALL, BRGY. TIBULOY, D.C. 2) TIBULOY ES, BRGY. TIBULOY, D.C. 3) ATAN-AWE BRGY. HALL, BRGY. ATAN-AWE, D.C. 4) SIBULAN BRGY. HALL, BRGY. SIBULAN, D.C. 5) MT. APO ES, BRGY. SIBULAN, D.C. 6) LAMANAN BG is a DPWH-tracked public work in Davao City 2nd DEO, Region XI. Reported contract value: ₱4,394,557.98. Status: Reported complete (DPWH). Contractor on record: R L CARABUENA CONST 35483. Figures trace to dpwh.

Davao City 2nd DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction Flood Mitigation Structure protecting Daang Maharlika (MN) at Brgy. Bunawan, Davao City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Davao City 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 35483

29 projects · ₱226.1M total · 0 flags

4. Implementation

Contract Amount

₱4,394,557.98

Progress

Reported complete (DPWH)

Start Date

December 6, 2022

Target End

March 5, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.