Roads23CE0181

CONCRETING OF BRGY. STA. MARIA FMR, BRGY. STA. MARIA, LICAB, NUEVA ECIJA

CONCRETING OF BRGY. STA. MARIA FMR, BRGY. STA. MARIA, LICAB, NUEVA ECIJA is a DPWH-tracked public work in Nueva Ecija 1st DEO, Region III. Reported contract value: ₱12,437,313.95. Status: Reported complete (DPWH). Contractor on record: IJK MAE CONST INC 35272. Figures trace to dpwh.

Nueva Ecija 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Casongsong River, Brgy. Casongsong, Guimba, Nueva Ecija
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Nueva Ecija 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱12,437,313.95

Progress

Reported complete (DPWH)

Start Date

May 22, 2023

Target End

November 7, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.