Roads20EI0185

CONCRETING OF BRGY. MALIWANAG TO BRGY. ROMA FMR, BRGY. MALIWANAG AND BRGY. ROMA, MANSALAY, ORIENTAL MINDORO

CONCRETING OF BRGY. MALIWANAG TO BRGY. ROMA FMR, BRGY. MALIWANAG AND BRGY. ROMA, MANSALAY, ORIENTAL MINDORO is a DPWH-tracked public work in Southern Mindoro DEO, Region IV-B. Reported contract value: ₱12,437,390.90. Status: Reported complete (DPWH). Contractor on record: AS YANG CONST 11322. Figures trace to dpwh.

Southern Mindoro DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱12,437,390.90

Progress

Reported complete (DPWH)

Start Date

September 20, 2020

Target End

March 17, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.