Water Provision and Storage25HJ0119

BASIC INFRASTRUCTURE PROGRAM (BIP)-PUBLIC WATER SUPPLY SYSTEM-CONSTRUCTION (COMPLETION) OF WATER WORK SYSTEM (LEVEL I AND II),BARANGAY TRINIDAD, GUIHULNGAN CITY, NEGROS ORIENTAL

BASIC INFRASTRUCTURE PROGRAM (BIP)-PUBLIC WATER SUPPLY SYSTEM-CONSTRUCTION (COMPLETION) OF WATER WORK SYSTEM (LEVEL I AND II),BARANGAY TRINIDAD, GUIHULNGAN CITY, NEGROS ORIENTAL is a DPWH-tracked public work in Negros Oriental 1st DEO, Negros Island Region. Reported contract value: ₱1,960,000.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: HIGEL CONST. Figures trace to dpwh.

Negros Oriental 1st DEO, Negros Island Region
Region: Negros Island Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱36,415,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bitoclan River, Guihulngan City, Negros Oriental
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Negros Oriental 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

11 projects · ₱54.4M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF 2STY WORKSHOP BUILDING IN MAGSAYSAY NATIONAL HIGH SCHOOL, CITY OF GUIHULNGAN, NEGROS ORIENTA

Negros Oriental 1st DEO, Negros Island Region

2024₱15.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BARANGAY IMELDA TO BARANGA

Negros Oriental 1st DEO, Negros Island Region

2025₱14.7M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM: MUTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT/EVACUATION CENTER), BARANGAY PANGCA, LA LIBERTAD, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2024₱4.9M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF COVERED COURT/ EVACUATION CENTER, DANAWAN, BINDOY, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2024₱4.9M
Reported complete (DPWH)
No sat.

Construction of Box Culvert along Mabinay-Ayungon Rd, Ayungon, Negros Oriental

AYUNGON (NEGROS ORIENTAL), NEGROS ORIENTAL, Region VII

2024₱2.9M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM: MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT/EVACUATION CENTER), BARANGAY TIGUIB, AYUNGON, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2024₱2.0M
Reported complete (DPWH)
View all 11 projects →

4. Implementation

Contract Amount

₱1,960,000.00

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 27, 2025

Target End

May 15, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.