Flood Control and Drainage17NB0075

CONST. OF HAMOGAWAY FLOOD CONTROL, PHASE II (DOWNSTREAM) ALONG DAANG MAHARLIKA, BAYUGAN, AGUSAN SUR

CONST. OF HAMOGAWAY FLOOD CONTROL, PHASE II (DOWNSTREAM) ALONG DAANG MAHARLIKA, BAYUGAN, AGUSAN SUR is a DPWH-tracked public work in Agusan del Sur 1st DEO, Region XIII. Reported contract value: ₱4,653,699.98. Status: Reported complete (DPWH). Contractor on record: DATREBIL CONST. Figures trace to dpwh.

Agusan del Sur 1st DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

130 projects · ₱2.1B total · 0 flags

Other projects by this contractor

View all 130 projects →

4. Implementation

Contract Amount

₱4,653,699.98

Progress

Reported complete (DPWH)

Start Date

June 8, 2017

Target End

September 15, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.