Buildings and Facilities17BK0060

CONSTRUCTION/IMPROVEMENT OF SAN MARCOS (PUROK 6) MPB SAN MARCOS, CABARROGUIS, QUIRINO

CONSTRUCTION/IMPROVEMENT OF SAN MARCOS (PUROK 6) MPB SAN MARCOS, CABARROGUIS, QUIRINO is a DPWH-tracked public work in Quirino DEO, Region II. Reported contract value: ₱2,475,000.00. Status: Reported complete (DPWH). Contractor on record: NTL BUILDERS AND DEVELOPER. Figures trace to dpwh.

Quirino DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 65%

UACS
18001
Amount
₱2,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Improvement of San Marcos (Purok 6) MPB, San Marcos, Cabarroguis, Quirino
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0021010

₱300,000,000.00 · FY2017

Released to Regional Field Unit - V (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

17BK0060(Re-Advertised) Construction/Improvement

₱2,408,478.03 · NTL BUILDERS & DEVELOPER

Contractor

B

179 projects · ₱4.0B total · 0 flags

4. Implementation

Contract Amount

₱2,475,000.00

Progress

Reported complete (DPWH)

Start Date

May 22, 2017

Target End

September 5, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.