Construction of Drainage Structure22KE0040

Construction of River Control/ Drainage System at Catibac Box Culvert, K47+000.00 - K47+212.50, K47+212.50 - K47+276.00, K47+212.50 - K47+231.50, K47.1+000 - K47.10+010.00, Catarman, Camiguin

Construction of River Control/ Drainage System at Catibac Box Culvert, K47+000.00 - K47+212.50, K47+212.50 - K47+276.00, K47+212.50 - K47+231.50, K47.1+000 - K47.10+010.00, Catarman, Camiguin is a DPWH-tracked public work in CATARMAN (CAMIGUIN), CAMIGUIN, Region X. Reported contract value: ₱19,600,000.00. Status: Reported complete (DPWH). Contractor on record: JAPUZ-JANSOL ENT. Figures trace to sumbong.

CATARMAN (CAMIGUIN), CAMIGUIN, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 77%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of River Flood Control System at Zone 2 and Zone 3 Dalla, Baggao, Cagayan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002934

₱165,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001639

₱5,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003062

₱5,000,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱19,600,000.00

Progress

Reported complete (DPWH)

Start Date

May 12, 2022

Target End

November 7, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.