Roads16N00023

CONSTRUCTION/OPENING OF ROAD, CABADBARAN - PUTING BATO - SITIO LUSONG - ADN/ADS BOUNDARY, CABADBARAN, AGUSAN DEL NORTE

CONSTRUCTION/OPENING OF ROAD, CABADBARAN - PUTING BATO - SITIO LUSONG - ADN/ADS BOUNDARY, CABADBARAN, AGUSAN DEL NORTE is a DPWH-tracked public work in Region XIII, Region XIII. Reported contract value: ₱131,623,640.94. Status: Reported complete (DPWH). Contractor on record: ADFIL CORP. Figures trace to dpwh.

Region XIII, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱131,623,640.94

Progress

Reported complete (DPWH)

Start Date

August 29, 2016

Target End

July 9, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.