Buildings and Facilities21OF0171

COMPLETION OF FOUR (4) STOREY EIGHT (8) CLASSROOM SCHOOL BUILDING AT SAN JOSE ELEMENTARY SCHOOL, QUEZON CITY

COMPLETION OF FOUR (4) STOREY EIGHT (8) CLASSROOM SCHOOL BUILDING AT SAN JOSE ELEMENTARY SCHOOL, QUEZON CITY is a DPWH-tracked public work in Quezon City 1st DEO, National Capital Region. Reported contract value: ₱4,433,260.00. Status: Reported complete (DPWH). Contractor on record: JYBL CORP FORMERLY: JYBL CONST. Figures trace to dpwh.

Quezon City 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along San Francisco River, Quezon City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Quezon City 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,433,260.00

Progress

Reported complete (DPWH)

Start Date

November 9, 2021

Target End

March 8, 2022

5. Audit