GAA 2023 CSSP23F00283

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF LABO RIVER CONTROL STRUCTURE, SITIO MANDALIG, BRGY. CAGBALOGO, VINZONS, CAMARINES NO

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF LABO RIVER CONTROL STRUCTURE, SITIO MANDALIG, BRGY. CAGBALOGO, VINZONS, CAMARINES NO is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱98,999,992.25. Status: Reported complete (DPWH). Contractor on record: ED1SON DEVELOPMENT & CONST INC. Figures trace to dpwh.

Region V, Region V
Region: Region V

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

92 projects · ₱7.5B total · 0 flags

4. Implementation

Contract Amount

₱98,999,992.25

Progress

Reported complete (DPWH)

Start Date

December 20, 2023

Target End

December 19, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.