Roads22IA0002

REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD - K1035+393 TO K1035+996 (124.37846°, 11.62938° TO 124.3745°, 11.63188°)

REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD - K1035+393 TO K1035+996 (124.37846°, 11.62938° TO 124.3745°, 11.63188°) is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱48,640,773.12. Status: Reported complete (DPWH). Contractor on record: E G CANABE CONST 27358. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Busali Flood Control along Biliran Circumferential Road, Biliran
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Biliran DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,640,773.12

Progress

Reported complete (DPWH)

Start Date

March 20, 2022

Target End

December 5, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.