Roads23PG0005

REHAB./RECONSTRUCTION OF ROADS W/ SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG BAN-HUNG-BENG BDRY RD.-K0371+812-K0371+875,K0371+816-K0371+842,K0371+848-K0371+875,K0373+240-K0373+260, HUNGDUAN, IFUGAO

REHAB./RECONSTRUCTION OF ROADS W/ SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG BAN-HUNG-BENG BDRY RD.-K0371+812-K0371+875,K0371+816-K0371+842,K0371+848-K0371+875,K0373+240-K0373+260, HUNGDUAN, IFUGAO is a DPWH-tracked public work in Ifugao 1st DEO, Cordillera Administrative Region. Reported contract value: ₱8,018,643.42. Status: Reported complete (DPWH). Contractor on record: MERJAN P HAMBON GEN CONST. Figures trace to dpwh.

Ifugao 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱39,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Lamut River, Sta. 18 + 300 - Sta. 18 + 850 (Lawig Side), Lamut, Ifugao
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Ifugao 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

27 projects · ₱273.5M total · 0 flags

4. Implementation

Contract Amount

₱8,018,643.42

Progress

Reported complete (DPWH)

Start Date

February 14, 2023

Target End

February 23, 2024

5. Audit