Flood Control and Drainage25BF0065

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF MALACOPA CREEK RIVER FLOOD CONTROL PROJECT ALONG PRESIDENT BRIDGE (DOWNSTREAM SECTION), BARANGAY DALIG-KALINGA, AURORA, ISABELA

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF MALACOPA CREEK RIVER FLOOD CONTROL PROJECT ALONG PRESIDENT BRIDGE (DOWNSTREAM SECTION), BARANGAY DALIG-KALINGA, AURORA, ISABELA is a DPWH-tracked public work in Isabela 2nd DEO, Region II. Reported contract value: ₱93,604,835.19. Status: Past target date (DPWH On-Going). Contractor on record: R E A CONST. Figures trace to dpwh.

Isabela 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Purok Eden and Purok Saranay, Barangay Sinamar, Roxas, Isabela
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Isabela 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱93,604,835.19

Progress

Past target date (DPWH On-Going)

Start Date

June 16, 2025

Target End

May 26, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.