Roads25B00014

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER 11239 - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS ALONG MANILA NORTH RD - K0646+000 - K0646+170, K0646+245 - K064

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER 11239 - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS ALONG MANILA NORTH RD - K0646+000 - K0646+170, K0646+245 - K064 is a DPWH-tracked public work in Region II, Region II. Reported contract value: ₱25,919,852.49. Status: Past target date (DPWH On-Going). Contractor on record: JEICCA BUILDERS. Figures trace to dpwh.

Region II, Region II
Region: Region II

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

60 projects · ₱1.2B total · 7 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SANTO TOMAS FLOOD CONTROL

Cagayan 2nd DEO, Region II

2025₱95.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF CABICUNGAN FLOOD CONTROL STRUC

Cagayan 2nd DEO, Region II

2025₱72.3M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, GUIDDAM, ABULUG, CAGAYAN

Cagayan 2nd DEO, Region II

2024₱49.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)- MULTI PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY GUIDDAM, ABULUG, CAGAYAN

Cagayan 2nd DEO, Region II

2025₱49.4M
Past target date (DPWH On-Going)
No sat.

Construction of Seawall along Shoreline of Ballesteros, Cagayan (Package 1)

BALLESTEROS (CAGAYAN), CAGAYAN, Region II

2024₱48.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF SEAWALL ALONG THE SHORELINE OF BALLESTEROS, PACKAGE 13,

Cagayan 2nd DEO, Region II

2024₱48.3M
Reported complete (DPWH)
View all 60 projects →

4. Implementation

Contract Amount

₱25,919,852.49

Progress

Past target date (DPWH On-Going)

Start Date

April 11, 2025

Target End

August 8, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.