GAA 2024 OO-224BD0120

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MGMT PROG. - CONST./ REHAB. OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONST. OF PINACANAUAN RIVER FLOOD MGMT PROJECTS, DODAN, PEÑABLANCA, CAGAYAN- PHASE II

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MGMT PROG. - CONST./ REHAB. OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONST. OF PINACANAUAN RIVER FLOOD MGMT PROJECTS, DODAN, PEÑABLANCA, CAGAYAN- PHASE II is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱34,178,254.49. Status: Past target date (DPWH On-Going). Contractor on record: DOUBLE J1908 CONST. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Pinacanauan River Flood Management Projects, Dodan, Peñablanca, Cagayan - Phase II
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Cagayan 3rd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

144 projects · ₱3.3B total · 0 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TUGUEGARAO-SOLANA DIVERSION ROAD (TUGUEGARAO- SOLANA BRIDGE AND APPROACHES), PHASE 3 (PACKAGE 2), CAGAYAN

Region II, Region II

2024₱270.0M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - TUGUEGARAO CITY BOULEVARD (PINACANAUAN BRIDGE 2 AND APPROACHES), PHASE 3 (PACKAGE 2) TUGUEGARAO CITY, CAGAYAN

Region II, Region II

2024₱264.5M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TUGUEGARAO - ENRILE DIVERSION ROAD (INCLUDING TUGUEGARAO - ENRILE BRIDGE AND APPROACHES, PHASE 3, CAGAYAN

Region II, Region II

2024₱237.9M
Past target date (DPWH On-Going)

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF TUGUEGARAO CIRCUMFERENTIAL DIKE ROAD, TUGUEGARA

Region II, Region II

2024₱183.0M
Reported complete (100% progress, DPWH status On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TUGUEGARAO - SOLANA DIVERSION ROAD (TUGUEGARAO - SOLANA BRIDGE AND APPROACHES), PACKAGE 1, CAGAYAN

Region II, Region II

2025₱141.7M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TUGUEGARAO - SOLANA DIVERSION ROAD (TUGUEGARAO - SOLANA BRIDGE AND APPROACHES), PACKAGE 2, CAGAYAN

Region II, Region II

2025₱141.7M
Past target date (DPWH On-Going)
View all 144 projects →

4. Implementation

Contract Amount

₱34,178,254.49

Progress

Past target date (DPWH On-Going)

Start Date

June 7, 2024

Target End

June 4, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.