Buildings and Facilities20DK0082

CONSTRUCTION OF ONE(1) STOREY THREE(3) CLASSROOM SCHOOL BUILDING CYNTHIA VILLAGE ELEMENTARY SCHOOL, GENERAL NAKAR, QUEZON

CONSTRUCTION OF ONE(1) STOREY THREE(3) CLASSROOM SCHOOL BUILDING CYNTHIA VILLAGE ELEMENTARY SCHOOL, GENERAL NAKAR, QUEZON is a DPWH-tracked public work in Quezon 1st DEO, Region IV-A. Reported contract value: ₱6,491,100.00. Status: Reported complete (DPWH). Contractor on record: FIRMABUILT CONST 30175. Figures trace to dpwh.

Quezon 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱6,491,100.00

Progress

Reported complete (DPWH)

Start Date

August 12, 2020

Target End

January 25, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.