Flood Control and Drainage18JE0058

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE CONSTRUCTION OF FLOOD CONTROL, BARANGAY ALANG-ALANG, TAMBULIG,ZAMBOANGA DEL SUR

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE CONSTRUCTION OF FLOOD CONTROL, BARANGAY ALANG-ALANG, TAMBULIG,ZAMBOANGA DEL SUR is a DPWH-tracked public work in Zamboanga del Sur 1st DEO, Region IX. Reported contract value: ₱9,333,296.57. Status: Reported complete (DPWH). Contractor on record: RUDHIL CONST. Figures trace to dpwh.

Zamboanga del Sur 1st DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱9,333,296.57

Progress

Reported complete (DPWH)

Start Date

June 19, 2018

Target End

September 16, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.