GAA 2018 OO-118K00120

CONST. OF BYPASS/ DIVERSION ROADS, GINGOOG BYPASS ROAD, INCL. ROW AND BRIDGE, MIS. OR.

CONST. OF BYPASS/ DIVERSION ROADS, GINGOOG BYPASS ROAD, INCL. ROW AND BRIDGE, MIS. OR. is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱119,146,478.53. Status: Reported complete (DPWH). Contractor on record: EQUI-PARCO CONST CO. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

725 projects · ₱77.9B total · 5 flags

4. Implementation

Contract Amount

₱119,146,478.53

Progress

Reported complete (DPWH)

Start Date

July 2, 2018

Target End

July 3, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.