Roads23L00021

CONSTRUCTION OF CONCRETE ROAD - FATIMA - MALABOG ROAD (MALABOG-GUMITAN), PACKAGE H, DAVAO CITY

CONSTRUCTION OF CONCRETE ROAD - FATIMA - MALABOG ROAD (MALABOG-GUMITAN), PACKAGE H, DAVAO CITY is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱84,961,838.22. Status: Reported complete (DPWH). Contractor on record: METRO GEAR CONST CORP 43024. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱84,961,838.22

Progress

Reported complete (DPWH)

Start Date

March 22, 2023

Target End

May 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.