Construction of Flood Mitigation Structure24EG0062

Construction of Flood Control Structure along Apurawan River Downstream (L/S), Aborlan, Palawan

Construction of Flood Control Structure along Apurawan River Downstream (L/S), Aborlan, Palawan is a DPWH-tracked public work in ABORLAN (PALAWAN), PALAWAN, Region IV-B. Reported contract value: ₱17,369,994.74. Status: Reported complete (DPWH). Contractor on record: G BANZ BUILDERS CORP. Figures trace to sumbong.

ABORLAN (PALAWAN), PALAWAN, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 99%

UACS
18001
Amount
₱18,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Apurawan River Downstream ( L / S ) , Aborlan, Palawan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008381

₱1,681,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0003151

₱464,327.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008395

₱155,000.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱17,369,994.74

Progress

Reported complete (DPWH)

Start Date

March 7, 2024

Target End

July 31, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.