Buildings and Facilities18DN0190

CONSTRUCTION OF 2 STOREY, 2 CLASSROOM, BAGONG NAYON I E/S, ANTIPOLO CITY, 1ST LD

CONSTRUCTION OF 2 STOREY, 2 CLASSROOM, BAGONG NAYON I E/S, ANTIPOLO CITY, 1ST LD is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱7,638,154.76. Status: Reported complete (DPWH). Contractor on record: STREAMLINE BUILDERS CORP 40804. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱7,638,154.76

Progress

Reported complete (DPWH)

Start Date

December 18, 2018

Target End

April 16, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.