Roads25PI0067

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM; ASSET PRESERVATION PROGRAM: CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS; SAGADA- BESAO- QUIRINO ROAD, CHAINAGE 239 - CHAINAGE 417, CHAI

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM; ASSET PRESERVATION PROGRAM: CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS; SAGADA- BESAO- QUIRINO ROAD, CHAINAGE 239 - CHAINAGE 417, CHAI is a DPWH-tracked public work in Mountain Province 1st DEO, Cordillera Administrative Region. Reported contract value: ₱2,506,332.56. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: YCO CONST 47958. Figures trace to dpwh.

Mountain Province 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Chico River, Sitio Cheka-a, Bontoc, Mountain Province
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Mountain Province 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,506,332.56

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

June 2, 2025

Target End

July 14, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.