Buildings and Facilities19KI0139

CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 1, BARANGAY SAN PEDRO, ALORAN, MISAMIS OCCIDENTAL.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 1, BARANGAY SAN PEDRO, ALORAN, MISAMIS OCCIDENTAL. is a DPWH-tracked public work in Misamis Occidental 1st DEO, Region X. Reported contract value: ₱968,885.38. Status: Reported complete (DPWH). Contractor on record: CMA CONST 41345. Figures trace to dpwh.

Misamis Occidental 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱968,885.38

Progress

Reported complete (DPWH)

Start Date

October 23, 2019

Target End

January 5, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.