Buildings and Facilities18LA0064

CONSTRUCTION (COMPLETION) OF BARANGAY HALL, BRGY. CABINUANGAN, NEW BATAAN, COMPOSTELA VALLEY PROVINCE

CONSTRUCTION (COMPLETION) OF BARANGAY HALL, BRGY. CABINUANGAN, NEW BATAAN, COMPOSTELA VALLEY PROVINCE is a DPWH-tracked public work in Davao de Oro 1st DEO, Region XI. Reported contract value: ₱985,329.00. Status: Reported complete (DPWH). Contractor on record: KANAWAY BUILDERS CORP. Figures trace to dpwh.

Davao de Oro 1st DEO, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Concrete Revetment along Cebulan River, Sta. Cruz, Davao del Sur
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Agency-level releases for FY2018, not tied to this contract

Davao de Oro 1st DEO · SARO 1,489 (₱126,676,811,675.00) · NCA 1,617 (₱426,584,627,343.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱985,329.00

Progress

Reported complete (DPWH)

Start Date

April 5, 2018

Target End

June 23, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.