Flood Control and Drainage17DN0115

CONSTRUCTION OF DRAINAGE SYSTEM, S. VICTORIA TO CAINTA RIVER, SAN JUAN, CAINTA, RIZAL

CONSTRUCTION OF DRAINAGE SYSTEM, S. VICTORIA TO CAINTA RIVER, SAN JUAN, CAINTA, RIZAL is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱2,821,152.39. Status: Reported complete (DPWH). Contractor on record: AYANA CONST AND TRADING. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱3,700,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Drainage Canal along Floodway Road Westbank, Rizal
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-C-17-0000692

₱100,000,000.00 · FY2017

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱2,821,152.39

Progress

Reported complete (DPWH)

Start Date

August 21, 2017

Target End

November 18, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.