Construction of Flood Mitigation Structure23GO0016

Construction of Flood Control Structure along Cabalagnan Creek, Phase 2, Barangay Pahanocoy, Bacolod City

Construction of Flood Control Structure along Cabalagnan Creek, Phase 2, Barangay Pahanocoy, Bacolod City is a DPWH-tracked public work in BACOLOD CITY (CAPITAL) (NEGROS OCCIDENTAL), NEGROS OCCIDENTAL, Region VI. Reported contract value: ₱49,000,000.00. Status: Reported complete (DPWH). Contractor on record: A C RIVERO DEVELOPMENT CORP. Figures trace to sumbong.

BACOLOD CITY (CAPITAL) (NEGROS OCCIDENTAL), NEGROS OCCIDENTAL, Region VI
Region: Region VI

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Cabalagnan Creek, Phase 2, Barangay Pahanocoy, Bacolod City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bacolod City District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

736 projects · ₱22.2B total · 19 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF BRIDGE, BARANGAY TALABAN, HIMAMAYLAN CITY, NEGROS OCCIDENTAL

Region VI, Region VI

2021₱183.3M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM: CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-LOCAL ROADS AND BRIDGES-LOCAL ROADS, CONSTRUCTION OF ROAD WITH SEAWALL, BARANGAY TABA-TABA TO BARANGAY MANGCAMAGONG, BASUD, CAMARINES NORTE, B

Region V, Region V

2020₱144.8M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING, PRIMARY ROADS DAANG MAHARLIKA (LZ),K0356+076-K0357+377.00; K0357+406-K0357+894.00; K0357+920.00-K0358+819.00, CAMARINES NORTE 2ND LEGISLATIVE DISTRICT

Region V, Region V

2020₱144.8M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM, OFF-CARRIAGEWAY IMPROVEMENT, TERTIARY ROADS: JUBAN-MAGALLANES ROAD, JUBAN AND MAGALLANES, SORSOGON PROVINCE

Region V, Region V

2018₱139.7M
Reported complete (DPWH)
No sat.

CONST. OF CONCRETE ROAD - BRGY. SAN ANTONIO - CONDEZ - SAN LUIS - SAN VICENTE - FLORES ROAD LEADING

Region VI, Region VI

2017₱134.8M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CLUSTER V-I-REHABILITATION/IMPROVEMENT OF REVETMENT ALONG BARANGAY BAGACAY-PACO SECTION, BOTH SIDE

Region V, Region V

2021₱130.4M
Past target date (DPWH On-Going)
View all 736 projects →

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Reported complete (DPWH)

Start Date

February 8, 2023

Target End

November 4, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.