Buildings and Facilities22L00132

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, AGDAO FARMERS MARKET, AGDAO, DAVAO CITY (PHASE I)

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, AGDAO FARMERS MARKET, AGDAO, DAVAO CITY (PHASE I) is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱96,476,604.44. Status: Past target date (DPWH On-Going). Contractor on record: THREE W BUILDERS INC 10722. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱96,476,604.44

Progress

Past target date (DPWH On-Going)

Start Date

September 5, 2022

Target End

July 17, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.