Roads18HF0096

CONCRETING OF BRGY. GIWANON FMR, BRGY. GIWANON, BARILI, CEBU

CONCRETING OF BRGY. GIWANON FMR, BRGY. GIWANON, BARILI, CEBU is a DPWH-tracked public work in Cebu 3rd DEO, Region VII. Reported contract value: ₱4,719,225.00. Status: Reported complete (DPWH). Contractor on record: YBK CONST. Figures trace to dpwh.

Cebu 3rd DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱4,719,225.00

Progress

Reported complete (DPWH)

Start Date

May 10, 2018

Target End

June 23, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.