Buildings and Facilities17IE0073

REHABILITATION OF RHU, CALUBIAN RHU, CALUBIAN, LEYTE

REHABILITATION OF RHU, CALUBIAN RHU, CALUBIAN, LEYTE is a DPWH-tracked public work in Leyte 3rd DEO, Region VIII. Reported contract value: ₱9,356,344.64. Status: Reported complete (DPWH). Contractor on record: RJIR ENT CORP. Figures trace to dpwh.

Leyte 3rd DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Rehabilitation of Hilongos Flood Control Structure, Hilongos, Leyte
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-16-0033091

₱38,917.00 · FY2016

Released to Taganaan National High School (Asa National HigRe (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

692 projects · ₱17.7B total · 35 flags

Other projects by this contractor

View all 692 projects →

4. Implementation

Contract Amount

₱9,356,344.64

Progress

Reported complete (DPWH)

Start Date

August 8, 2017

Target End

January 4, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.