Flood Control and Drainage18CI0078

FLOOD MANAGEMENT PROGRAM; CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM, CONSTRUCTION OF REINFORCED CONCRETE SLOPE PROTECTION WITH STEEL SHEET PILES FOUNDATION ALONG SAPANG BATO RIVER, BRGY MARGOT TO BRGY ANUNAS, A.C., PAMP.

FLOOD MANAGEMENT PROGRAM; CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM, CONSTRUCTION OF REINFORCED CONCRETE SLOPE PROTECTION WITH STEEL SHEET PILES FOUNDATION ALONG SAPANG BATO RIVER, BRGY MARGOT TO BRGY ANUNAS, A.C., PAMP. is a DPWH-tracked public work in Pampanga 3rd DEO, Region III. Reported contract value: ₱23,034,452.87. Status: Reported complete (DPWH). Contractor on record: ARROWHEAD CONST. Figures trace to dpwh.

Pampanga 3rd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱24,402,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Reinforced Concrete Slope Protection with Steel Sheet Piles Foundation along Taug River, Brgy. Margot to Brgy. Anunas, Angeles City, Pampanga
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0008955

₱0.00 · FY2018

Released to Division of Pampanga (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

24 projects · ₱479.8M total · 4 flags

4. Implementation

Contract Amount

₱23,034,452.87

Progress

Reported complete (DPWH)

Start Date

June 8, 2018

Target End

November 4, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.