GAA 2025 OO-225FG0065

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BAHAY RIVER, (UPSTREAM OF BAHAY BRIDGE) PACKAGE 2, CARAMOAN, CAMARINES SUR

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BAHAY RIVER, (UPSTREAM OF BAHAY BRIDGE) PACKAGE 2, CARAMOAN, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 4th DEO, Region V. Reported contract value: ₱37,039,901.39. Status: Past target date (DPWH On-Going). Contractor on record: E A SANCHO CONST INC FORM E A SANCHO CONST. Figures trace to dpwh.

Camarines Sur 4th DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱45,390,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Tagas Bridge, Jct. Nato-Sabang, Camarines Sur
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Camarines Sur 4th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

113 projects · ₱3.8B total · 0 flags

Other projects by this contractor

View all 113 projects →

4. Implementation

Contract Amount

₱37,039,901.39

Progress

Past target date (DPWH On-Going)

Start Date

June 26, 2025

Target End

January 15, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.