Flood Control and Drainage17CL0095

CONSTRUCTION OF SLOPE PROTECTION/FLOOD CONTROL, LAUIS RIVER CONTROL, CANDELARIA, ZAMBALES

CONSTRUCTION OF SLOPE PROTECTION/FLOOD CONTROL, LAUIS RIVER CONTROL, CANDELARIA, ZAMBALES is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱14,285,365.94. Status: Reported complete (DPWH). Contractor on record: CDC CONST. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Slope Protection/Flood Control, Lauis River Control, Candelaria, Zambales
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-17-0022649

₱7,844.00 · FY2017

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱14,285,365.94

Progress

Reported complete (DPWH)

Start Date

May 30, 2017

Target End

November 25, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.