Roads19CG0093

CONSTRUCTION / REHABILITATION OF MEXICO -MAGALANG ROAD / NINOY AQUINO BYWAY (ANAO, MEXICO - SAN ANTONIO, ARAYAT SECTION) MEXICO AND ARAYAT, PAMPANGA

CONSTRUCTION / REHABILITATION OF MEXICO -MAGALANG ROAD / NINOY AQUINO BYWAY (ANAO, MEXICO - SAN ANTONIO, ARAYAT SECTION) MEXICO AND ARAYAT, PAMPANGA is a DPWH-tracked public work in Pampanga 1st DEO, Region III. Reported contract value: ₱27,830,485.40. Status: Reported complete (DPWH). Contractor on record: DAUNGAN CONST DEV'T. Figures trace to dpwh.

Pampanga 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

80 projects · ₱707.8M total · 0 flags

Other projects by this contractor

No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF MALISIK - MABATO - SALAPUNGAN ROAD, CANDABA, PAMPANGA

Pampanga 1st DEO, Region III

2024₱47.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF SLOPE PROTECTION WORKS AT MAASIM RIVER, PHASE II (TRIBUTARY OF PAMPANGA RIVER) BARANGAY PULONG GUBAT, CANDABA, PAMPANGA

Pampanga 1st DEO, Region III

2023₱32.1M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, STA. ANA CENTRAL HIGH SCHOOL, STA. LUCIA, STA. ANA, PAMPANGA

Pampanga 1st DEO, Region III

2023₱27.8M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SLOPE PROTECTION ALONG PAMPANGA RIVER, STA. 0+000 - STA. 0+023, CANDATING SECTION, ARAYAT, PAMPANGA

Pampanga 1st DEO, Region III

2021₱27.1M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROADS INCLUDING DRAINAGE CANAL, CANDABA, PAMPANGA

Pampanga 1st DEO, Region III

2024₱26.8M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF BARANGAY PALIGUI ROAD WITH DRAINAGE CANAL, BARANGAY PALIGUI, AP

Pampanga 1st DEO, Region III

2022₱25.9M
Reported complete (DPWH)
View all 80 projects →

4. Implementation

Contract Amount

₱27,830,485.40

Progress

Reported complete (DPWH)

Start Date

July 19, 2019

Target End

December 15, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.