Roads20DP0042

NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROAD - SAN PABLO- CALAUAN RD. - K0081 + 095 - K0081 + 586, K0081 + 593 - K0082 + 000

NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROAD - SAN PABLO- CALAUAN RD. - K0081 + 095 - K0081 + 586, K0081 + 593 - K0082 + 000 is a DPWH-tracked public work in Laguna 3rd DEO, Region IV-A. Reported contract value: ₱26,054,280.00. Status: Reported complete (DPWH). Contractor on record: R'CEL GEN CONTRACTOR. Figures trace to dpwh.

Laguna 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Contstruction of Flood Control Structure, Brgy. San Francisco, Biñan, Laguna
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Laguna 3rd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱26,054,280.00

Progress

Reported complete (DPWH)

Start Date

November 20, 2020

Target End

May 18, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.