Flood Control and Drainage25PF0020

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BUAS NABUSUKAN COMMUNAL IRRIGATION SYSTEM (CIS), BUGUIAS, BENGUET

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BUAS NABUSUKAN COMMUNAL IRRIGATION SYSTEM (CIS), BUGUIAS, BENGUET is a DPWH-tracked public work in Benguet 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱14,686,764.90. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: NORJOHN CONST. Figures trace to dpwh.

Benguet 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 97%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Buas Nabusukan Communal Irrigation System (CIS), Buguias, Benguet
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Benguet 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱14,686,764.90

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 4, 2025

Target End

July 29, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.