Roads16CL0012

CONCRETING OF ROAD PHASE 3, KAWAYAN- KILING ROAD, BARANGAY AMUNGAN, IBA, ZAMBALES 2ND LD

CONCRETING OF ROAD PHASE 3, KAWAYAN- KILING ROAD, BARANGAY AMUNGAN, IBA, ZAMBALES 2ND LD is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱9,414,582.67. Status: Reported complete (DPWH). Contractor on record: CDC CONST. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱9,414,582.67

Progress

Reported complete (DPWH)

Start Date

March 28, 2016

Target End

July 15, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.