Bridges19AB0071

REPLACEMENT OF PERMANENT WEAK BRIDGES, STO. TOMAS BRIDGE 1 (B00804LZ) ALONG PINILI-NUEVA ERA ROAD/PINILI, ILOCOS NORTE

REPLACEMENT OF PERMANENT WEAK BRIDGES, STO. TOMAS BRIDGE 1 (B00804LZ) ALONG PINILI-NUEVA ERA ROAD/PINILI, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 2nd DEO, Region I. Reported contract value: ₱47,594,062.32. Status: Reported complete (DPWH). Contractor on record: NORTH TECH BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Ilocos Norte 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-LGRCB-19-0003441

₱2,100,000.00 · FY2019

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱47,594,062.32

Progress

Reported complete (DPWH)

Start Date

June 21, 2019

Target End

July 21, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.