Buildings and Facilities17BD0019

LIP: CONSTRUCTION OF 1 CLASSROOM, BUGATAY ELEMENTARY SCHOOL, PEÑABLNCA, CAGAYAN, CAGAYAN 3RD LD

LIP: CONSTRUCTION OF 1 CLASSROOM, BUGATAY ELEMENTARY SCHOOL, PEÑABLNCA, CAGAYAN, CAGAYAN 3RD LD is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱952,853.12. Status: Reported complete (DPWH). Contractor on record: JOHN 6:51 BUILDERS. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System, Sta. 0+240 – Sta. 0+540, Brgy. Fugu, Tuao, Cagayan
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Agency-level releases for FY2017, not tied to this contract

Cagayan 3rd DEO · SARO 1,101 (₱106,257,715,220.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

90 projects · ₱398.0M total · 0 flags

4. Implementation

Contract Amount

₱952,853.12

Progress

Reported complete (DPWH)

Start Date

February 21, 2017

Target End

May 21, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.