Buildings and Facilities19LA0277

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BRGY. PANANSALAN, COMPOSTELA, COMPOSTELA VALLEY PROVINCE

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BRGY. PANANSALAN, COMPOSTELA, COMPOSTELA VALLEY PROVINCE is a DPWH-tracked public work in Davao de Oro 1st DEO, Region XI. Reported contract value: ₱3,135,156.81. Status: Reported complete (DPWH). Contractor on record: MARK ANTHONY CONST. Figures trace to dpwh.

Davao de Oro 1st DEO, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱3,135,156.81

Progress

Reported complete (DPWH)

Start Date

July 17, 2019

Target End

October 14, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.