Bridges16R00066

CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS-WIDENING OF PERMANENT BRIDGES GUINDASCAN BR. (B00164NR), ALONG BACOLOD NORTH ROAD, NEGROS OCCIDENTAL

CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS-WIDENING OF PERMANENT BRIDGES GUINDASCAN BR. (B00164NR), ALONG BACOLOD NORTH ROAD, NEGROS OCCIDENTAL is a DPWH-tracked public work in Region VI, Region VI. Reported contract value: ₱10,868,518.75. Status: Reported complete (DPWH). Contractor on record: WTG CONST. Figures trace to dpwh.

Region VI, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

298 projects · ₱12.8B total · 0 flags

Other projects by this contractor

CONSTRUCTION OF STORM SURGE PROTECTION: HEIGHTENED ROAD AND TIDE EMBANKMENT, STATION 1+900 - STATION 2+550, SECTION 5 PHASE 9, BRGY. SAN JOAQUIN, PALO, LEYTE

Region VIII, Region VIII

2018₱263.4M
Reported complete (DPWH)

CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG MAJOR RIVER BASINS AND PRINCIPAL RIVERS AT SIPALAY RIVER

Region VI, Region VI

2018₱195.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF FLYOVERS/INTERCHANGES/UNDERPASSES/LONG SPAN BRIDGES PANGLAO-TAGBILARAN CITY OFFSHORE BRIDGE, SECTION 1: STA.000+000-STA.000+223.21, SECTION

Region VII, Region VII

2020₱193.0M
Reported complete (DPWH)
No sat.

CSSP, SUSTAINABLE INFRA PROJ. ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BLDG./ FACILITIES, CONST. OF ROAD FROM TABON TO BARANGAY GUBA LEADING TO BINAKAYAN, VALLEHERMOSO,NEGROS ORIENTAL

Region VII, Region VII

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PINOCAWAN RIVER, VALLEHERMOSO, NEGROS ORIENTAL

Region VII, Region VII

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BATERIA RIVER, GUIHULNGAN CITY, NEGROS ORIENTAL

Region VII, Region VII

2024₱193.0M
Past target date (DPWH On-Going)
View all 298 projects →

4. Implementation

Contract Amount

₱10,868,518.75

Progress

Reported complete (DPWH)

Start Date

September 27, 2016

Target End

January 4, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.