Roads21K00255

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, MASTERSON AVENUE ALTERNATE ROAD, CAGAYAN DE ORO CITY

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, MASTERSON AVENUE ALTERNATE ROAD, CAGAYAN DE ORO CITY is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱77,607,739.18. Status: Reported complete (DPWH). Contractor on record: VEN RAY CONST CORP. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2021 GAA. DBM GAA FY2021

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱77,607,739.18

Progress

Reported complete (DPWH)

Start Date

September 24, 2021

Target End

February 1, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.